HH0-210 · Question #66
You are planning an initial VSP installation at a customer site. Which two must be verified? (Choose two.)
The correct answer is A. sufficient service clearance at the front and back sides C. availability of a LAN access. See the full explanation below for the reasoning.
Question
You are planning an initial VSP installation at a customer site. Which two must be verified? (Choose two.)
Options
- Asufficient service clearance at the front and back sides
- Bsufficient service clearance at the right and left sides
- Cavailability of a LAN access
- Davailability of an analog modem line
How the community answered
(45 responses)- A76% (34)
- B7% (3)
- D18% (8)