Huawei
H35-211_V2.5 · Question #468
GPON system DBA scheduling is only for upstream traffic and cannot schedule downstream traffic.
The correct answer is A. True. See the full explanation below for the reasoning.
FTTx Solutions and Deployment
Question
GPON system DBA scheduling is only for upstream traffic and cannot schedule downstream traffic.
Options
- ATrue
- BFalse
How the community answered
(23 responses)- A83% (19)
- B17% (4)
Topics
#GPON DBA#upstream scheduling#dynamic bandwidth allocation
Community Discussion
No community discussion yet for this question.