H35-211_V2.5 · Question #442

In the POL network planning process, what output options are provided to users to guide project delivery and network software commissioning implementation? (Multiple choice)

The correct answer is B. Low-level design documentation C. LLD. See the full explanation below for the reasoning.

FTTx Solutions and Deployment

Question

In the POL network planning process, what output options are provided to users to guide project delivery and network software commissioning implementation? (Multiple choice)

Options

  • AHLD
  • BLow-level design documentation
  • CLLD
  • DHigh-level design document

How the community answered

(41 responses)
  • A
    7% (3)
  • B
    80% (33)
  • D
    12% (5)

Topics

#POL network planning#HLD LLD documentation#project delivery#design output

Community Discussion

No community discussion yet for this question.