In the POL network planning process, what output options are provided to users to guide project delivery and network software commissioning implementation? (Multiple choice)
The correct answer is B. Low-level design documentation C. LLD. See the full explanation below for the reasoning.
FTTx Solutions and Deployment
Question
In the POL network planning process, what output options are provided to users to guide project delivery and network software commissioning implementation? (Multiple choice)
Options
- AHLD
- BLow-level design documentation
- CLLD
- DHigh-level design document
How the community answered
(41 responses)- A7% (3)
- B80% (33)
- D12% (5)
Topics
#POL network planning#HLD LLD documentation#project delivery#design output