Question

The optical and electronic racks of the OSN 9800 equipment communicate through master-slave sub-rack cascading, and are connected through the GE1/2 ports on the CTU single board.

Options

  • ATrue
  • BFalse

Unlock H31-341_V2.5 to see the answer