In the network management planning process, which item is not absolutely necessary?

The correct answer is B. DON network planning, OSS docking planning. See the full explanation below for the reasoning.

Question

In the network management planning process, which item is not absolutely necessary?

Options

  • ANetwork scale planning, network management deployment planning
  • BDON network planning, OSS docking planning
  • CNetwork parameter planning and reliability planning of the network management server
  • DNetwork management software and hardware configuration

How the community answered

(36 responses)
  • A
    8% (3)
  • B
    78% (28)
  • C
    11% (4)
  • D
    3% (1)