Huawei
H31-341_V2.5 · Question #698
Which of the following options are included in the half-yearly maintenance project on the network management side? (Multiple choice)
The correct answer is A. Backup network element data B. Active/standby switchover C. Check ECC routing D. Test protection switching. See the full explanation below for the reasoning.
Question
Which of the following options are included in the half-yearly maintenance project on the network management side? (Multiple choice)
Options
- ABackup network element data
- BActive/standby switchover
- CCheck ECC routing
- DTest protection switching
How the community answered
(30 responses)- A100% (30)
Community Discussion
No community discussion yet for this question.