When the main control board is single-configured, which step is required to replace the single board compared to when the main control board is dual-configured?

The correct answer is A. Download the original configuration data. See the full explanation below for the reasoning.

Question

When the main control board is single-configured, which step is required to replace the single board compared to when the main control board is dual-configured?

Options

  • ADownload the original configuration data
  • BMake sure that the host software version is consistent before and after the replacement, if not, please
  • CConsistency check of network management and network element data.
  • DQuery the alarms of the board and confirm that the original alarms have been cleared.

How the community answered

(33 responses)
  • A
    85% (28)
  • B
    3% (1)
  • C
    3% (1)
  • D
    9% (3)