Which of the following description about single-station commissioning is wrong?
The correct answer is C. In the case of power failure, you don't need to wear anti-static wrist or anti-static gloves to touch the. See the full explanation below for the reasoning.
Question
Which of the following description about single-station commissioning is wrong?
Options
- AIf the input voltage of the equipment is not within the required range, suggestions for rectification should
- BIt is strictly forbidden to plug and unplug the power plug and PIU board with power on
- CIn the case of power failure, you don't need to wear anti-static wrist or anti-static gloves to touch the
- DAfter the single station hardware inspection is completed, make sure that all power switches are in the
How the community answered
(32 responses)- A3% (1)
- B16% (5)
- C75% (24)
- D6% (2)