H19-301_V4.0 · Question #103
[Huawei Data Center Network Products and Solutions] Which of the following steps are used to implement automatic network migration during the upgrade from a legacy N7-5-2 network to an SDN network?
The correct answer is A. Gateway migration: Migrate north-south gateways from the legacy network to the new network. B. Live network analysis: Review configurations on the N7-5-2 network. C. Layer 2 interconnection: Interconnect the legacy and new networks at Layer 2. D. Service migration: Migrate VMs or servers (in batches). You've hit your limit · resets 1pm (America/New_York)
Data Center Network Presales and Solution Overview
Question
[Huawei Data Center Network Products and Solutions] Which of the following steps are used to implement automatic network migration during the upgrade from a legacy N7-5-2 network to an SDN network?
Options
- AGateway migration: Migrate north-south gateways from the legacy network to the new network.
- BLive network analysis: Review configurations on the N7-5-2 network.
- CLayer 2 interconnection: Interconnect the legacy and new networks at Layer 2.
- DService migration: Migrate VMs or servers (in batches).
How the community answered
(26 responses)- A100% (26)
Explanation
You've hit your limit · resets 1pm (America/New_York)
Topics
#SDN migration#legacy network upgrade#Layer 2 interconnection#service migration