At 12:00 AM, a company's data center experienced a downtime, and its applications went offline. The maximum downtime allowed was four hours. After the company implemented emergency measures, the…
The correct answer is A. RTO=3h, RPO=15h. See the full explanation below for the reasoning.
Business Continuity and Disaster Recovery Architecture
Question
At 12:00 AM, a company's data center experienced a downtime, and its applications went offline. The maximum downtime allowed was four hours. After the company implemented emergency measures, the data center was restored at 3:00 AM. The company backs up system data daily, with the last backup occurring at 9:00 AM the previous day. Which of the following descriptions of RTO and RPO indicators is correct?
Options
- ARTO=3h, RPO=15h
- BRTO=9h, RPO=3h
- CRTO=4h, RPO=9h
- DRTO=4h, RPO=24h
How the community answered
(30 responses)- A80% (24)
- B10% (3)
- C3% (1)
- D7% (2)
Topics
#RTO#RPO#DR metrics calculation#downtime recovery
Community Discussion
No community discussion yet for this question.