At 12:00 AM, a company's data center experienced a downtime, and its applications went offline. The maximum downtime allowed was four hours. After the company implemented emergency measures, the…

The correct answer is A. RTO=3h, RPO=15h. See the full explanation below for the reasoning.

Business Continuity and Disaster Recovery Architecture

Question

At 12:00 AM, a company's data center experienced a downtime, and its applications went offline. The maximum downtime allowed was four hours. After the company implemented emergency measures, the data center was restored at 3:00 AM. The company backs up system data daily, with the last backup occurring at 9:00 AM the previous day. Which of the following descriptions of RTO and RPO indicators is correct?

Options

  • ARTO=3h, RPO=15h
  • BRTO=9h, RPO=3h
  • CRTO=4h, RPO=9h
  • DRTO=4h, RPO=24h

How the community answered

(30 responses)
  • A
    80% (24)
  • B
    10% (3)
  • C
    3% (1)
  • D
    7% (2)

Topics

#RTO#RPO#DR metrics calculation#downtime recovery