The Fusioninsight HD cluster planned by a bank has 90 nodes. If three control nodes are planned, it is recommended to plan () data nodes in the cluster.
The correct answer is A. 87. See the full explanation below for the reasoning.
Question
The Fusioninsight HD cluster planned by a bank has 90 nodes. If three control nodes are planned, it is recommended to plan () data nodes in the cluster.
Options
- A87
- B85
- C90
- D86
How the community answered
(54 responses)- A81% (44)
- B6% (3)
- C2% (1)
- D11% (6)