Due to business development needs, an enterprise plans to purchase Huawei all-flash storage devices to replace old storage (and migrate the data of the old storage to the newly purchased storage…

The correct answer is A. Service interruption caused by source LUN failure B. The host's multipath software may need to be upgraded, and services may be affected during the D. Service interruption caused by host restart. See the full explanation below for the reasoning.

Storage O&M and Troubleshooting

Question

Due to business development needs, an enterprise plans to purchase Huawei all-flash storage devices to replace old storage (and migrate the data of the old storage to the newly purchased storage devices. What risks does Engineer A need to consider when performing data migration? (Multiple choice)

Options

  • AService interruption caused by source LUN failure
  • BThe host's multipath software may need to be upgraded, and services may be affected during the
  • CWhen the new storage takes over the old storage business, it will inevitably cause business
  • DService interruption caused by host restart

How the community answered

(34 responses)
  • A
    76% (26)
  • C
    24% (8)

Topics

#migration risk assessment#LUN failure#multipath software#business continuity