For migration in an AD domain environment, after the migration is completed, the target storage needs to replace the source storage. Which one needs to be consistent with the source storage?

The correct answer is A. At least the domain name must be the same. See the full explanation below for the reasoning.

Storage O&M and Troubleshooting

Question

For migration in an AD domain environment, after the migration is completed, the target storage needs to replace the source storage. Which one needs to be consistent with the source storage?

Options

  • AAt least the domain name must be the same
  • BEither the domain name or the IP address should be consistent.
  • CThe domain name and IP must be consistent
  • DOnly need to keep the IP consistent

How the community answered

(34 responses)
  • A
    79% (27)
  • B
    3% (1)
  • C
    6% (2)
  • D
    12% (4)

Topics

#AD domain migration#NAS migration#domain name consistency#storage replacement

Community Discussion

No community discussion yet for this question.

Full H13-629_V3.0 Practice