H13-629_V3.0 · Question #696

A customer project deploys 8-node Huawei OceanStor 9000 C Node, with full IB networking at the front and back ends. The equipment has been powered on and the intercommunication test between all…

The correct answer is C. Before starting the software deployment, the project configures a temporary backend IP address on. See the full explanation below for the reasoning.

Advanced NAS Storage Architecture and Design

Question

A customer project deploys 8-node Huawei OceanStor 9000 C Node, with full IB networking at the front and back ends. The equipment has been powered on and the intercommunication test between all equipment front-end network ports and the customer front-end service switches has been completed. Next, the engineer will install and deploy the Huawei OceanStor 900 software. The following are some of the operations performed by the engineer during the on-site deployment process. Which one complies with the operating specifications?

Options

  • ADeploy the software directly without disconnecting the front-end network and all storage nodes.
  • BConnect the installation PC directly to the OM management network switch via a network cable to
  • CBefore starting the software deployment, the project configures a temporary backend IP address on
  • DThe engineer believes that the software deployment can be completed by connecting the installation

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    14% (4)
  • C
    79% (22)
  • D
    4% (1)

Topics

#OceanStor 9000#software deployment#NAS deployment procedure#on-site commissioning