Due to the National Day, the equipment needs to be powered off and then powered on for maintenance. What is the correct order for powering on?
The correct answer is B. External power -> controller box power -> switch power -> server power. See the full explanation below for the reasoning.
Storage O&M and Troubleshooting
Question
Due to the National Day, the equipment needs to be powered off and then powered on for maintenance. What is the correct order for powering on?
Options
- AExternal power -> server power -> controller box power -> switch power
- BExternal power -> controller box power -> switch power -> server power
- CExternal power -> server power -> switch power -> controller box power
- DExternal power -> controller box power -> server power -> switch power
How the community answered
(21 responses)- A10% (2)
- B81% (17)
- C5% (1)
- D5% (1)
Topics
#power-on sequence#storage maintenance#O&M procedures#data center operations