Huawei
H13-629_V3.0 · Question #550
After the storage project is transferred and maintained, which one does not belong to the standard process management link?
The correct answer is A. Disaster Recovery Management. See the full explanation below for the reasoning.
Storage O&M and Troubleshooting
Question
After the storage project is transferred and maintained, which one does not belong to the standard process management link?
Options
- ADisaster Recovery Management
- BProblem Management
- CConfiguration Management
- DEvent Management
How the community answered
(34 responses)- A82% (28)
- B3% (1)
- C6% (2)
- D9% (3)
Topics
#ITIL process#problem management#configuration management#event management