The company plans to deploy a DR system to ensure that services are not interrupted and service data is not lost when a data center fails. If a 3DC architecture is used , a 3DC solution with two…

The correct answer is A. True. See the full explanation below for the reasoning.

Data Protection and Business Continuity Solution Design

Question

The company plans to deploy a DR system to ensure that services are not interrupted and service data is not lost when a data center fails. If a 3DC architecture is used , a 3DC solution with two active DCs can meet the requirements.

Options

  • ATrue
  • BFalse

How the community answered

(58 responses)
  • A
    79% (46)
  • B
    21% (12)

Topics

#3DC architecture#active-active#disaster recovery#RPO RTO