nerdexam
Huawei

H13-629_V3.0 · Question #518

Customer M built a primary-backup disaster recovery system using Huawei storage products, requiring operation and maintenance personnel to periodically inspect and maintain the system, and also…

The correct answer is A. When testing the disaster recovery network at the disaster recovery end, maintenance personnel B. To achieve tolerance test by snapshot mapping on the disaster recovery side. The test process will C. When the production center fails, the designated recovery plan can be executed for planned D. After the test is completed, the drill data on the disaster recovery side needs to be cleaned up to. See the full explanation below for the reasoning.

Data Protection and Business Continuity Solution Design

Question

Customer M built a primary-backup disaster recovery system using Huawei storage products, requiring operation and maintenance personnel to periodically inspect and maintain the system, and also requiring the disaster recovery center to conduct irregular disaster recovery tests to verify the feasibility of the disaster recovery solution. Which of the following statements about the customer's disaster recovery test operations are correct? (Multiple choice)

Options

  • AWhen testing the disaster recovery network at the disaster recovery end, maintenance personnel
  • BTo achieve tolerance test by snapshot mapping on the disaster recovery side. The test process will
  • CWhen the production center fails, the designated recovery plan can be executed for planned
  • DAfter the test is completed, the drill data on the disaster recovery side needs to be cleaned up to

How the community answered

(18 responses)
  • A
    100% (18)

Topics

#DR testing#snapshot mapping#recovery plan#drill cleanup

Community Discussion

No community discussion yet for this question.

Full H13-629_V3.0 Practice