H13-629_V3.0 · Question #216
In Huawei's active-standby disaster recovery solution, which of the following descriptions is the correct process for disaster recovery failover?
The correct answer is B. 1. Force switching of replication relationship. See the full explanation below for the reasoning.
Data Protection and Business Continuity Solution Design
Question
In Huawei's active-standby disaster recovery solution, which of the following descriptions is the correct process for disaster recovery failover?
Options
- A
- Stop production applications and unmap the host.
- B
- Force switching of replication relationship.
- C
- Create a snapshot on the disaster recovery side.
- D
- Unlock the host computer.
How the community answered
(24 responses)- A8% (2)
- B71% (17)
- C4% (1)
- D17% (4)
Topics
#disaster recovery failover#active-standby#replication relationship#failover process