Bank M plans to build a remote disaster recovery center. The distance between the disaster recovery center and the production center is about 1000 km. Which of the following statements are correct…
The correct answer is A. The bank's production center and disaster recovery center need to adopt asynchronous remote B. Network bandwidth needs to take into account of changes in business data in the production center C. The write delay of the front-end application of the bank's storage system has nothing to do with the. See the full explanation below for the reasoning.
Data Protection and Business Continuity Solution Design
Question
Bank M plans to build a remote disaster recovery center. The distance between the disaster recovery center and the production center is about 1000 km. Which of the following statements are correct when the bank builds the remote disaster recovery center? (Multiple choice)
Options
- AThe bank's production center and disaster recovery center need to adopt asynchronous remote
- BNetwork bandwidth needs to take into account of changes in business data in the production center
- CThe write delay of the front-end application of the bank's storage system has nothing to do with the
- DNetwork bandwidth design does not need to consider cycle
How the community answered
(30 responses)- A80% (24)
- D20% (6)
Topics
#remote disaster recovery#asynchronous replication#network bandwidth#long-distance DR