H13-629_V3.0 · Question #140
The customer plans to migrate data based on the virtualization platform migration solution. The actual total capacity of the dual-machine system that needs to be migrated is 100TB. The target…
The correct answer is B. 210.9 hours. See the full explanation below for the reasoning.
Storage O&M and Troubleshooting
Question
The customer plans to migrate data based on the virtualization platform migration solution. The actual total capacity of the dual-machine system that needs to be migrated is 100TB. The target storage is planned to have 50 LNs and 200 virtual machines. The migration bandwidth is 150MB/s. Which of the following is the estimated data migration time?
Options
- A120.5 hours
- B210.9 hours
- C280.74 hours
- D4.24 hours
How the community answered
(25 responses)- B84% (21)
- C12% (3)
- D4% (1)
Topics
#data migration time calculation#migration bandwidth#virtualization migration#capacity planning