H13-629_V3.0 · Question #140

The customer plans to migrate data based on the virtualization platform migration solution. The actual total capacity of the dual-machine system that needs to be migrated is 100TB. The target…

The correct answer is B. 210.9 hours. See the full explanation below for the reasoning.

Storage O&M and Troubleshooting

Question

The customer plans to migrate data based on the virtualization platform migration solution. The actual total capacity of the dual-machine system that needs to be migrated is 100TB. The target storage is planned to have 50 LNs and 200 virtual machines. The migration bandwidth is 150MB/s. Which of the following is the estimated data migration time?

Options

  • A120.5 hours
  • B210.9 hours
  • C280.74 hours
  • D4.24 hours

How the community answered

(25 responses)
  • B
    84% (21)
  • C
    12% (3)
  • D
    4% (1)

Topics

#data migration time calculation#migration bandwidth#virtualization migration#capacity planning

Community Discussion

No community discussion yet for this question.

Full H13-629_V3.0 Practice