After deploying Huawei all-flash storage as the backend storage of the application server, you need to power on the devices involved in sequence to check the operating status. Please associate the…

The correct answer is A. 1- Turn on the external power switch corresponding to each device B. 2- Turn on the power switch of the storage device interconnection switch C. 3-Turn on the power switch of each controller box in turn D. 4- Turn on the power switch of the application server. See the full explanation below for the reasoning.

Storage O&M and Troubleshooting

Question

After deploying Huawei all-flash storage as the backend storage of the application server, you need to power on the devices involved in sequence to check the operating status. Please associate the following device power-on operations with their corresponding sequence. (Multiple choice)

Options

  • A1- Turn on the external power switch corresponding to each device
  • B2- Turn on the power switch of the storage device interconnection switch
  • C3-Turn on the power switch of each controller box in turn
  • D4- Turn on the power switch of the application server

How the community answered

(32 responses)
  • A
    100% (32)

Topics

#power-on sequence#device startup#storage deployment#controller