Huawei
H13-629_V3.0 · Question #1179
H13-629_V3.0 Question #1179: Real Exam Question with Answer & Explanation
The correct answer is A. Check the connection status between the host HBA card and the storage system B. Export configuration data on the storage side C. Reclaim WWNs, mapping views, LUN groups, port groups, and host groups D. Delete the Zone related configuration on the switch. See the full explanation below for the reasoning.
Question
In Huawei All-Flash Storage, storage device space reclamation is divided into full reclamation and partial reclamation. Please analyze which of the following items belong to the main operation flow of the reclamation phase in the full reclamation scenario? (Multiple choice)
Options
- ACheck the connection status between the host HBA card and the storage system
- BExport configuration data on the storage side
- CReclaim WWNs, mapping views, LUN groups, port groups, and host groups
- DDelete the Zone related configuration on the switch
Community Discussion
No community discussion yet for this question.