In order to ensure business reliability, after deploying Huawei BCManager to protect the business from disaster, disaster recovery drills can be conducted regularly. Which of the following is not a…

The correct answer is B. Create a snapshot on the disaster recovery end. See the full explanation below for the reasoning.

Data Protection and Business Continuity Solution Design

Question

In order to ensure business reliability, after deploying Huawei BCManager to protect the business from disaster, disaster recovery drills can be conducted regularly. Which of the following is not a step that needs to be performed during disaster recovery drills?

Options

  • ASynchronize incremental data
  • BCreate a snapshot on the disaster recovery end
  • CSwitching relationship
  • DStart the disaster recovery application

How the community answered

(29 responses)
  • A
    17% (5)
  • B
    72% (21)
  • C
    3% (1)
  • D
    7% (2)

Topics

#BCManager#disaster recovery drill#DR steps#incremental synchronization