nerdexam
Huawei

H13-629_V3.0 · Question #1045

In the planning and design of active-standby disaster recovery solutions, when synchronous remote technology is used between the production center and the disaster recovery center, the bandwidth…

The correct answer is B. False. See the full explanation below for the reasoning.

Data Protection and Business Continuity Solution Design

Question

In the planning and design of active-standby disaster recovery solutions, when synchronous remote technology is used between the production center and the disaster recovery center, the bandwidth calculation method is the same as the active-active disaster recovery bandwidth.

Options

  • ATrue
  • BFalse

How the community answered

(29 responses)
  • A
    21% (6)
  • B
    79% (23)

Topics

#synchronous replication#bandwidth planning#active-standby DR#disaster recovery design

Community Discussion

No community discussion yet for this question.