H13-629_V3.0 · Question #1037

H13-629_V3.0 Question #1037: Real Exam Question with Answer & Explanation

The correct answer is A. True. See the full explanation below for the reasoning.

Question

Through the cross-data center dual-active + asynchronous two-site three-center solution, the RPO of the same city business can be achieved = 0, RTO = 0, and the RPO of the remote disaster recovery center can be achieved in minutes through the multi-time point technology.

Options

  • ATrue
  • BFalse