A financial customer newly purchased several Huawei distributed storages for business deployment, with a total of 6 nodes, including 2 computing nodes and 4 storage nodes, and the business, storage…

The correct answer is C. In this scenario, engineers do not need to plan aggregation interfaces, but must plan 8 MGT. See the full explanation below for the reasoning.

Question

A financial customer newly purchased several Huawei distributed storages for business deployment, with a total of 6 nodes, including 2 computing nodes and 4 storage nodes, and the business, storage, and management switches were deployed independently. An engineer needs to plan interfaces for a 25GE switch. Which of the following descriptions about interface planning is wrong?

Options

  • AIn interface planning, engineers can reserve interfaces. To shut down reserved interfaces,
  • BIf engineers want to plan M-LAG interfaces, each switch can use two 100GE interfaces to
  • CIn this scenario, engineers do not need to plan aggregation interfaces, but must plan 8 MGT
  • DIf engineers want to plan node interfaces, each switch can use 4 to 6 25GE interfaces to connect

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    4% (1)
  • C
    78% (18)
  • D
    4% (1)