In the HyperMetro active-active data center solution, data centers A and B are included. When the array of data center A fails, which of the following statements is correct? (Multiple choice)
The correct answer is A. Multi-path automatically sets all paths to data center A to be unavailable, and all IOs are directly B. The array in data center B records the difference bitmap for the newly received I/O. C. After the failure of the array in data center A recovers, the active-active relationship is D. The array in data center A actively powers off, and sends a command to the array in data center. See the full explanation below for the reasoning.
Question
In the HyperMetro active-active data center solution, data centers A and B are included. When the array of data center A fails, which of the following statements is correct? (Multiple choice)
Options
- AMulti-path automatically sets all paths to data center A to be unavailable, and all IOs are directly
- BThe array in data center B records the difference bitmap for the newly received I/O.
- CAfter the failure of the array in data center A recovers, the active-active relationship is
- DThe array in data center A actively powers off, and sends a command to the array in data center
How the community answered
(71 responses)- A100% (71)
Community Discussion
No community discussion yet for this question.