An enterprise plans to use the time when the business is not busy on the National Day to power off the IT room for circuit safety maintenance. After the circuit maintenance is completed, it is…

The correct answer is B. External power supply --> controller enclosure power supply --> switch power supply --> server. See the full explanation below for the reasoning.

Question

An enterprise plans to use the time when the business is not busy on the National Day to power off the IT room for circuit safety maintenance. After the circuit maintenance is completed, it is necessary to power on the power-off equipment. Which of the following equipment power-on sequences is correct?

Options

  • AExternal power supply --> controller enclosure power supply --> server power supply --> switch
  • BExternal power supply --> controller enclosure power supply --> switch power supply --> server
  • CExternal power supply --> server power supply -> switch power supply --> controller enclosure
  • DExternal power supply --> server power supply > controller enclosure power supply --> switch

How the community answered

(61 responses)
  • A
    15% (9)
  • B
    70% (43)
  • C
    10% (6)