Backup and Disaster Recovery Technologies
Question
The company plans to deploy a DR system to ensure that services are not interrupted and service data is not lost when a data center fails. If a 3DC architecture is used, a 3DC solution with two active DCs can meet the requirements.
Options
- ATrue
- BFalse
How the community answered
(43 responses)- A81% (35)
- B19% (8)
Topics
#3DC architecture#active-active DC#disaster recovery#RPO RTO