Question

A company plans to use the National Day holiday when business is not busy to shut down the power supply of computer room I for circuit safety maintenance. After the circuit maintenance is completed, the powered-off equipment needs to be powered on. Which of the following equipment power-on sequence is correct?

Options

  • AExternal power supply -> server power supply -> switch power supply -> controller box power
  • BExternal power -> server power -> controller box power -> switch power
  • CExternal power -> controller box power -> server power -> switch power
  • DExternal power supply -> controller box power supply -> switch power supply -> server power