A company plans to use the National Day holiday when business is not busy to shut down the power supply of computer room I for circuit safety maintenance. After the circuit maintenance is completed…

The correct answer is D. External power supply -> controller box power supply -> switch power supply -> server power. See the full explanation below for the reasoning.

Huawei Storage Product Overview

Question

A company plans to use the National Day holiday when business is not busy to shut down the power supply of computer room I for circuit safety maintenance. After the circuit maintenance is completed, the powered-off equipment needs to be powered on. Which of the following equipment power-on sequence is correct?

Options

  • AExternal power supply -> server power supply -> switch power supply -> controller box power
  • BExternal power -> server power -> controller box power -> switch power
  • CExternal power -> controller box power -> server power -> switch power
  • DExternal power supply -> controller box power supply -> switch power supply -> server power

How the community answered

(17 responses)
  • A
    18% (3)
  • B
    6% (1)
  • C
    6% (1)
  • D
    71% (12)