In Keystone, the ownership of resources belongs to which of the following objects?

The correct answer is B. Project. See the full explanation below for the reasoning.

Question

In Keystone, the ownership of resources belongs to which of the following objects?

Options

  • AService
  • BProject
  • CRole
  • DUser

How the community answered

(25 responses)
  • A
    16% (4)
  • B
    72% (18)
  • C
    8% (2)
  • D
    4% (1)