nerdexam
Huawei

H12-921_V1.0 · Question #161

What are the correct items in the following description of lossless network architecture design in multivariate computing scenarios?

The correct answer is A. In the case of a two-level network, the Spine switch does not have an uplink interface, and all ports B. When designing a network architecture, a bottom-up approach is generally used to determine how C. In two-tier networking, the number of Spine switches is equal to the total number of upstream D. First, the total number of network access interfaces is determined according to the number of. All four options are correct statements about lossless network architecture design in high-performance/multivariate computing environments. Option A is correct because in a two-tier (Spine-Leaf) topology, Spine switches sit at the top of the hierarchy with no upstream devices…

Data Center Network Evolution and Architecture

Question

What are the correct items in the following description of lossless network architecture design in multivariate computing scenarios?

Options

  • AIn the case of a two-level network, the Spine switch does not have an uplink interface, and all ports
  • BWhen designing a network architecture, a bottom-up approach is generally used to determine how
  • CIn two-tier networking, the number of Spine switches is equal to the total number of upstream
  • DFirst, the total number of network access interfaces is determined according to the number of

How the community answered

(27 responses)
  • A
    100% (27)

Explanation

All four options are correct statements about lossless network architecture design in high-performance/multivariate computing environments. Option A is correct because in a two-tier (Spine-Leaf) topology, Spine switches sit at the top of the hierarchy with no upstream devices, so they have no uplink ports - all ports connect downward to Leaf switches. Option B is correct because network architects use a bottom-up design methodology, starting from compute node counts and access-layer requirements, then deriving upstream bandwidth and switch counts layer by layer. Option C is correct because in two-tier design, every Leaf switch must have one uplink to each Spine switch to ensure full-mesh connectivity and equal-cost multipathing; therefore, the number of Spine switches equals the number of uplink ports per Leaf. Option D is correct because the process begins by counting server/node access interfaces, which anchors the entire capacity-planning chain.

Since this is an "all of the above" question with no distractors, the key exam trap is assuming one or more options must be false - don't fall for it.

Memory tip: Think of Spine-Leaf design as bottom-up, full-mesh, no uplinks at top - if you remember those three principles, you can validate all four statements quickly under exam pressure.

Topics

#Spine-Leaf Architecture#Two-tier Networking#Network Capacity Planning#Design Methodology

Community Discussion

No community discussion yet for this question.

Full H12-921_V1.0 Practice