Huawei
H12-891_V1.0 · Question #300
Which of the following channels is established between the CPE and the independently deployed RR in Huawei's SD-WAN solution?
The correct answer is B. Control channel. See the full explanation below for the reasoning.
SDN and Network Automation
Question
Which of the following channels is established between the CPE and the independently deployed RR in Huawei's SD-WAN solution?
Options
- AAuthentication channel
- BControl channel
- CManagement channel
- DData channel
How the community answered
(39 responses)- A8% (3)
- B74% (29)
- C15% (6)
- D3% (1)
Topics
#SD-WAN#CPE#route reflector#control channel