Huawei
H12-831_V1.0 · Question #360
A large Internet service provider needs to shut down the equipment in the computer room for maintenance in batches. As a cutover project manager, which of the following time points would you prefer?
The correct answer is D. Working Days. See the full explanation below for the reasoning.
Question
A large Internet service provider needs to shut down the equipment in the computer room for maintenance in batches. As a cutover project manager, which of the following time points would you prefer?
Options
- ALabor Day
- BNational Day
- CWeekend
- DWorking Days
How the community answered
(53 responses)- A6% (3)
- B4% (2)
- C15% (8)
- D75% (40)
Community Discussion
No community discussion yet for this question.