H12-831_V1.0 · Question #360

A large Internet service provider needs to shut down the equipment in the computer room for maintenance in batches. As a cutover project manager, which of the following time points would you prefer?

The correct answer is D. Working Days. See the full explanation below for the reasoning.

Question

A large Internet service provider needs to shut down the equipment in the computer room for maintenance in batches. As a cutover project manager, which of the following time points would you prefer?

Options

  • ALabor Day
  • BNational Day
  • CWeekend
  • DWorking Days

How the community answered

(53 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    15% (8)
  • D
    75% (40)