In the network shown in the figure, the network engineer found that the path between PC1 and PC2 is not the optimal path, and the cost value of each link is the same. Based on this analysis, which…

The correct answer is C. SW1 0; SW2 32768; SW3 8192; SW4 4096. See the full explanation below for the reasoning.

Question

In the network shown in the figure, the network engineer found that the path between PC1 and PC2 is not the optimal path, and the cost value of each link is the same. Based on this analysis, which of the following priorities may the switch have?

Exhibit

H12-831_V1.0 question #235 exhibit

Options

  • ASW1 32768; SW2 4096; SW3 0; SW4 8192
  • BSW1 32768; SW2 0; SW3 4096; SW4 8192
  • CSW1 0; SW2 32768; SW3 8192; SW4 4096
  • DSW1 32768; SW2 12288; SW3 4096; SW4 8192

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    8% (2)
  • C
    73% (19)
  • D
    4% (1)