Huawei
H12-831_V1.0 · Question #167
As the scale of the enterprise network continues to expand, a certain enterprise plans to move the dispersed servers to the same computer room for unified management. At a certain stage of the…
The correct answer is B. False. See the full explanation below for the reasoning.
Question
As the scale of the enterprise network continues to expand, a certain enterprise plans to move the dispersed servers to the same computer room for unified management. At a certain stage of the relocation, the work content is hardware relocation. At this stage, the network engineer does not need to perform equipment commissioning, so the network engineer does not need to formulate a cutover plan.
Options
- ATrue
- BFalse
How the community answered
(46 responses)- A22% (10)
- B78% (36)
Community Discussion
No community discussion yet for this question.