H12-721 · Question #107

An enterprise network cutover has just been done. The old network equipment is off the assembly line and the line is now on new network equipment. After operational testing we found that the…

The correct answer is C. substitution method. See the full explanation below for the reasoning.

Question

An enterprise network cutover has just been done. The old network equipment is off the assembly line and the line is now on new network equipment. After operational testing we found that the majority of traffic will not work. What will be administrators quickest way to restore business?

Options

  • Astratification
  • BBreak Law
  • Csubstitution method
  • DBlock Method

How the community answered

(46 responses)
  • A
    13% (6)
  • B
    2% (1)
  • C
    80% (37)
  • D
    4% (2)