In the implementation steps of the IS027001 project, which of the following does not belong to the system design and release phase?

The correct answer is C. Convene a project summary meeting during the information security management phase. See the full explanation below for the reasoning.

Question

In the implementation steps of the IS027001 project, which of the following does not belong to the system design and release phase?

Options

  • ASystem integration and information security management system document preparation
  • BDetermine risk treatment measures and implement rectification plans
  • CConvene a project summary meeting during the information security management phase
  • DDetermine risk tolerance and risk appetite

How the community answered

(60 responses)
  • A
    3% (2)
  • B
    5% (3)
  • C
    83% (50)
  • D
    8% (5)