H12-425_V2.0 · Question #97

H12-425_V2.0 Question #97: Real Exam Question with Answer & Explanation

Sign in or unlock H12-425_V2.0 to reveal the answer and full explanation for question #97. The question stem and answer options stay visible for context.

Question

Using UPS5000-E (50kVA power module), the actual load is 160kW, the rack is 1+1 redundant, the single-machine backup power scheme is adopted, the backup power scheme for each machine, 3 sets of batteries per rack, 40 cells per set, the capacity of the main switch box is:

Options

  • A630A
  • B500A
  • C250A
  • D320A