At present, in the design of the data center, the part ( ) that most affects the PUE.

The correct answer is B. Refrigeration system. See the full explanation below for the reasoning.

Question

At present, in the design of the data center, the part ( ) that most affects the PUE.

Options

  • APower supply and distribution system
  • BRefrigeration system
  • CDecoration system
  • DBuilding Systems

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    80% (24)
  • C
    3% (1)
  • D
    7% (2)