Commissioning NetCol5000-C drainage devices, after lifting the high float for 5 seconds, two water pumps start working, and the drain abnormal alarm is generated.
The correct answer is A. True. See the full explanation below for the reasoning.
Question
Commissioning NetCol5000-C drainage devices, after lifting the high float for 5 seconds, two water pumps start working, and the drain abnormal alarm is generated.
Options
- ATrue
- BFalse
How the community answered
(56 responses)- A73% (41)
- B27% (15)
Community Discussion