H12-425_V2.0 · Question #522

Commissioning NetCol5000-C drainage devices, after lifting the high float for 5 seconds, two water pumps start working, and the drain abnormal alarm is generated.

The correct answer is A. True. See the full explanation below for the reasoning.

Question

Commissioning NetCol5000-C drainage devices, after lifting the high float for 5 seconds, two water pumps start working, and the drain abnormal alarm is generated.

Options

  • ATrue
  • BFalse

How the community answered

(56 responses)
  • A
    73% (41)
  • B
    27% (15)