Commissioning NetCol5000-C drainage devices, after lifting the high float for 5 seconds, two water pumps start working, and the drain abnormal alarm is generated.

The correct answer is B. False. See the full explanation below for the reasoning.

Question

Commissioning NetCol5000-C drainage devices, after lifting the high float for 5 seconds, two water pumps start working, and the drain abnormal alarm is generated.

Options

  • ATrue
  • BFalse

How the community answered

(30 responses)
  • A
    30% (9)
  • B
    70% (21)