Question

The output terminals of the LPS2000-G-6/10/15/20K include sL and pL. Which of the following statements about the terminals is false?

Options

  • AWhen UPSs are connected in parallel, connect loads to the pL terminal.
  • BWhen a single US works and loads are of the same importance connect all loads to the sL terminal.
  • CWhen a single UPS works and lauds are divided into two levels connect the primary load to the sL terminal
  • DWhen the UPS is overloaded, the loads connected to the sL terminal il be powered of first to ensure

Unlock H12-425_V2.0 to see the answer

You've previewed enough free H12-425_V2.0 questions. Unlock H12-425_V2.0 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.