H12-425_V2.0 · Question #280
When the UPS is in parallel, the input phase sequence of the main bypass of each UPS needs to be checked, and the output phase sequence of a single pair is not required.
The correct answer is B. FALSE. See the full explanation below for the reasoning.
Question
When the UPS is in parallel, the input phase sequence of the main bypass of each UPS needs to be checked, and the output phase sequence of a single pair is not required.
Options
- ATRUE
- BFALSE
How the community answered
(18 responses)- A28% (5)
- B72% (13)