H12-425_V2.0 · Question #201
After the UPS5000-E is installed, what are the key points for the first power-on inspection? (Multiple choice)
The correct answer is A. Whether the mechanical installation and cable installation are tight B. Input and output without short circuit C. AC input phase sequence is correct D. Battery wiring is correct. See the full explanation below for the reasoning.
Question
After the UPS5000-E is installed, what are the key points for the first power-on inspection? (Multiple choice)
Options
- AWhether the mechanical installation and cable installation are tight
- BInput and output without short circuit
- CAC input phase sequence is correct
- DBattery wiring is correct
How the community answered
(30 responses)- A100% (30)