The NetEco management system supports dispatching corresponding work orders for a certain alarm to track the entire processing process. What type of work order is this?

The correct answer is C. Alert Work Order. See the full explanation below for the reasoning.

Question

The NetEco management system supports dispatching corresponding work orders for a certain alarm to track the entire processing process. What type of work order is this?

Options

  • AAsset Work Order
  • BChange Work Order
  • CAlert Work Order
  • DBusiness Work Order

How the community answered

(47 responses)
  • A
    9% (4)
  • B
    4% (2)
  • C
    74% (35)
  • D
    13% (6)