H12-223 · Question #165

Which three parts do the project TCO mainly contain?

The correct answer is B. Construction investment, operation and maintenance, optimization and transformation. See the full explanation below for the reasoning.

Question

Which three parts do the project TCO mainly contain?

Options

  • ATime cost, labor cost, resource cost
  • BConstruction investment, operation and maintenance, optimization and transformation
  • CRecruitment, personnel maintenance, personnel management
  • DEquipment procurement, equipment racking, equipment maintenance

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    78% (21)
  • C
    4% (1)
  • D
    7% (2)