Huawei
H12-223 · Question #124
Which of the following contents is not negotiated on a project kick-off meeting?
The correct answer is B. Verify implementation costs. See the full explanation below for the reasoning.
Question
Which of the following contents is not negotiated on a project kick-off meeting?
Options
- ADetermine customer's requirements.
- BVerify implementation costs.
- CConfirm owners of party A and party B.
- DDetermine the project management regulations.
How the community answered
(25 responses)- A12% (3)
- B80% (20)
- C4% (1)
- D4% (1)
Community Discussion
No community discussion yet for this question.