If a fault cannot be rectified in a short time on a complex network but the customer needs to restore network availability immediately, which of the following actions is recommended?

The correct answer is C. Communicate with the customer on skipping the faulty node, and set up an alternative network. See the full explanation below for the reasoning.

Question

If a fault cannot be rectified in a short time on a complex network but the customer needs to restore network availability immediately, which of the following actions is recommended?

Options

  • ATell the customer that this is impossible.
  • BSet up an alternative network environment.
  • CCommunicate with the customer on skipping the faulty node, and set up an alternative network
  • DAttempt to rectify the fault. If the fault cannot be rectified after a period of time, communicate with

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    9% (2)
  • C
    73% (16)
  • D
    14% (3)

Community Discussion

No community discussion yet for this question.

Full H12-223 Practice